Fiber Network Deployment Progress

FIberOptic Internet for:  Ariel, Yale, Amboy & Cougar, WA

Overall Network Completion
50%

Construction Timeline

Last updated on: 11/21/23

STARTING SOON

PHASE 2: Fiber to the home

This phase is underway, and we will be updating this in the near future.

STARTING SOON

COMPLETED

PHASE 2: Contruction Proposals

The Port of Woodland bidding process is underway for Phase 2 (Fiber to the home). The Port will be awarding the winning company for construction by the end of November 2033.

COMPLETED

PHASE 1: Backbone Completion

The Port of Woodland has completed the backbone construction.

COMPLETED

6/1/2022

PHASE 1: Backbone start date

Fiberoptic backbone project start date for phase 1 construction.